Budget management ================= Budget management is based on the subtask time tracking, the user timetable and the user hourly rate. This section is available from project settings page: **Project > Budget**. There is also a shortcut from the dropdown menu on the board. Budget lines ------------ ![Cost Lines](http://kanboard.net/screenshots/documentation/budget-lines.png) Budget lines are used to define a budget for the project. This budget can be adjusted by adding a new entry with an effective date. Cost breakdown -------------- ![Cost Breakdown](http://kanboard.net/screenshots/documentation/budget-cost-breakdown.png) Based on the subtask time tracking table and user information you can see the cost of each subtask. The time spent is rounded to nearest quarter. Budget graph ------------ ![Budget Graph](http://kanboard.net/screenshots/documentation/budget-graph.png) Finally, by combining all information we can generate a graph: - Expenses represents user cost - Budget lines are the provisioned budget - Remaining is the budget left at the given time