Budget management
=================
Budget management is based on the subtask time tracking, the user timetable and the user hourly rate.
This section is available from project settings page: **Project > Budget**. There is also a shortcut from the dropdown menu on the board.
Budget lines
------------
![Cost Lines](http://kanboard.net/screenshots/documentation/budget-lines.png)
Budget lines are used to define a budget for the project.
This budget can be adjusted by adding a new entry with an effective date.
Cost breakdown
--------------
![Cost Breakdown](http://kanboard.net/screenshots/documentation/budget-cost-breakdown.png)
Based on the subtask time tracking table and user information you can see the cost of each subtask.
The time spent is rounded to nearest quarter.
Budget graph
------------
![Budget Graph](http://kanboard.net/screenshots/documentation/budget-graph.png)
Finally, by combining all information we can generate a graph:
- Expenses represents user cost
- Budget lines are the provisioned budget
- Remaining is the budget left at the given time
|