Calendar
========
There are two different views for the calendar:
- The project view with filters (available from the board)
- The user view (available from the dashboard and from the user section)
At this time the calendar is able to display these information:
- Tasks with a due date, displayed at the top. The date can be changed by moving the task to another day.
- Tasks based on the creation date or the start date. These events cannot be modified with the calendar.
- Subtask time tracking, all recorded time slot will be shown in the calendar.
- Subtask estimates, forecast of work left
![Calendar](http://kanboard.net/screenshots/documentation/calendar.png)
The calendar configuration can be changed in the settings page.
|